TIME LIMIT |
COST |
|
|
|
a) Provision of application forms& Information |
Immediate |
Free |
|
|
|
b) Processing of investment certificate |
2 days |
500 $ USD |
|
|
|
c) Access to utilities (water& electricity): |
|
|
Connection to the grid |
24 hours |
30,000 Rwf |
Line extension |
1 month |
6,000 Rwf |
|
|
|
d) Processing of exemption on imported goods (Capital goods,raw materials, other investment related inputs ): |
|
|
Forms processing |
15 minutes |
Free |
|
|
|
e) Collection of non fiscal revenues |
Immediate |
Free |
|
|
|
f) Notary services |
30 minutes |
Variable fee |
|
|
|
g) Immigration services |
|
50,000 Rwf |
Visa&work permit |
1 hour |
50,000 Rwf |
Renewal of Visa&Work permit |
30 minutes |
|
|
|
|
h) Environmental Compliance: |
|
|
|
Immediate |
Free |
- Site visit and issuance of Terms of reference
|
2 weeks |
Free |
- EIA report review and issuance of EIA Certificate
|
20 days |
Free |